Project Description
Goodyear – Americana – SP
Material and Labor supply for the execution and installation of the plant expansion of the Americana – SP site.
Period; 4 years (48 months)
Brief summary of activities:
- Facilities (Electrical Package #2, #3, #4 and #5):
- 7500 kVA Primary Substation (SEP 5 and 6) / 2300 V Power distribution;
- Factory Substation 11, 13, 901, 1001, 1002, 1101, 1201;
- Lighting Substation 18 and 19. Readjustment of SEIs 1, 2, 4, 6, 7 and 14.
- Mixers (Electrical Package #4): Banbury #7
- body area network
- dust colletor
- carbon black
- twin screw; batch off
- Intercom system
- 480 V power distribution.
- Preparatory (Equipment Setting #1) :
- Extruder – 8X8Hexaplex;
- Calander – Cal. 4R1, Cal 4R2 and Wire Calander (Cal. Z);
- Cutters – Fischer, Mini slitter, Mother roll and Calemard; Bead Winder.
- Tire Building Room (Eq. Sett. #1, Elec. Pack. #3, Phase 1.5):
- Consumer: 06 TBM’s HF, 04 Apexers (Nakatas) All new conveyor system (Green Tire #1, #2, and #3)
- Commercial: Mesnac
- Curing (Eq. Sett. #1, Elec. Pack. #3):
- 20 presses 46″ and 06 presses 52“
- Final Finish (Phase 1 and 1.5):
- Zone 15: All Conveyors System
- Zones 16 and 17: Inspection Table
- Zones 18 and 20: FVM and DBM Sorter
- Zones 19 and 21: FVM and DBM Takeaway
Peak mobilized labor; 640 people